Customer
INA – Industrija nafte d.d. (Croatia)
Task & Solution
Our team recently completed a comprehensive quality-control supervision project as part of a major refinery upgrade, which included the installation of a new petcoke storage silo and coke-handling system. As an Ex-certified company, we carried out supervision and inspections within hazardous (Ex) zones, ensuring full compliance with safety and industry standards. Our scope covered the oversight of electrical equipment installation, detailed instrumentation work, and the systematic completion of all required Quality Control Forms for each project phase.
In addition to quality-control duties, our engineers performed a range of technical tasks, including configuring Schneider PLCs for integration with the refinery’s SCADA system for main-substation monitoring and control, as well as executing thorough I/O checks to verify system readiness.