Customer:
Neste / RDCG Upgrade Project
Task & Solution:
As part of the refinery upgrade project in Rotterdam, new storage tanks, process equipment, and instrumentation were installed and integrated into the existing facility. Before commissioning and start-up, all newly installed systems required thorough verification and functional testing.
The work began with pre-loop inspections, following the client’s checklist to verify mechanical and electrical installations, connections, and wiring against the provided drawings and technical documentation.
During the pre-loop testing phase, we independently tested the functionality of field instruments, including control valves, transmitters, sensors, and motor-related signals. This involved verifying signals, alarms, fault indications, operating status, and valve positions, as applicable. We also performed diagnostics and troubleshooting using HART Communicators and investigated issues across field instrumentation, Distributed Control Systems (DCS), and Safety Instrumented Systems (SIS), resolving identified faults before proceeding.
Once the instruments were verified and functioning correctly, we performed the final loop checks together with the client, demonstrating and verifying the operation of each instrument and its associated signals. Failure scenarios, including wire breaks and power supply interruptions, were simulated where applicable to confirm correct system responses and alarm functionality.
Through this systematic approach, we helped ensure that the installed instrumentation and control interfaces met project requirements and were ready for commissioning and start-up.